Cubic Yard (CY)

also called CY, yard

One cubic yard equals 27 cubic feet (3 × 3 × 3 ft) or about 0.7646 cubic meters. Concrete, gravel, and bulk earthwork are sold and bid by the cubic yard in US construction.

Unit conversions: 1 CY = 27 ft³ = 0.7646 m³. To convert cubic feet to cubic yards, divide by 27. To convert m³ to CY, multiply by 1.30795. To convert CY to m³, multiply by 0.7646.

Volume math in CY: a 30 × 20 × 0.333 ft slab (30 × 20 ft footprint at 4 inches thick) equals 200 ft³, or 7.41 CY. Concrete is sold in 1/4 CY increments; round 7.41 up to 7.5 CY for ordering (add waste percentage first).

Density-derived mass: 1 CY of compacted earth at 1,660 kg/m³ weighs approximately 1.4 short tons. 1 CY of concrete at 2,400 kg/m³ weighs about 2.0 short tons. Tonnage matters for trucking capacity (a tandem dump holds 10-14 CY loose; a tri-axle 14-18 CY).

Related terms
  • Ready-Mix Concrete
  • Loose Volume
  • Bank Volume
Use the math
  • Concrete yardage calculator
  • Earthwork volume calculator
From terminology to bid

Vertigraph builds the takeoff software estimators actually use.

BidScreen XL adds PDF and CAD measurement directly to Excel. SiteWorx/OS handles earthwork cut and fill from drawings. Try either free for 14 days.

Start 14 day free trialSee all products
Vertigraph

Takeoff and estimating software for commercial contractors across the United States.

800.989.4243 · 214.340.9436
support@vertigraph.com
Products
  • BidScreen XL
  • SiteWorx/OS
  • Drawing Compare (add on)
  • Pricing
Resources
  • Free calculators
  • Estimating guides
  • Glossary
  • Compare takeoff software
  • Pricing guide 2026
Support
  • FAQs
  • Training videos
  • Product documents
  • Contact
  • BidPoint XL (legacy)
Company
  • About
  • History
  • Blog
  • Testimonials
  • Partners
  • Students
© 2026 Vertigraph, Inc. All rights reserved.
TermsPrivacySitemap